Permit Requirement List
| Job
Address: |
Permit
No. : |
Date: |
| Job
Description: |
| Contractor's
Name/Address: |
Tel.
No: |
- Please provide a signed and sealed topographic
survey by a Florida registered professional land
surveyor.
- Submit (4) sets of design drawings certified
by a Florida registered professional engineer (Engineer
of Record). Plans should clearly identify the limits
of work and locations of all existing and proposed
utilities. Plans must include plan and profile
views of all utility construction. All standard
details must conform to the City of Fort Lauderdale
standard details. Contact engineering dept. to
obtain a copy of the City of Fort Lauderdale Construction
Standards and Specifications.
-
Supply all applicable permits/licenses
with the engineering permit application.
- Broward County DNRP - Stormwater Construction
License
- Broward County DNRP - Wastewater Construction
License
- Broward County DNRP - General Construction
License
- Broward County Public Health Unit - Water
Construction License
- Broward County Public Health Unit - Septic
Tank Construction License
- FDOT Permits (or at least intent to issue
letter)
- FDEP
- South Florida Water Management District
Stormwater Permit
- Other
-
Submit (4) sets of shop drawings
approved by the engineer of record for all materials
to be utilized in the right-of-way. Material
shop drawing approvals are subject to the review
and acceptance of the City of Fort Lauderdale
Engineering Department. Some examples of required
shop drawings are:
- Pipe, fittings, valves, restraining mechanisms,
hydrants, etc.
- Valve vaults, manholes, catch basins with
associated rims/grates
- Asphalt and concrete type or mix design
- Standard proctors.
- Provide a detailed cost estimate for all work
to be performed in the right-of-way. Include all
restoration items such as taps, pipes & fittings,
valves, sidewalk restoration, excavation & backfill,
striping, asphalt base and compaction densities.
- Submit cash bond equal to 150 percent of the
construction costs in the right-of-way and easement(s)
up to $100,000 construction value. For construction
values that exceed $100,000, a performance bond
equal to 100 percent of the construction costs
in the right-of-way and easement(s) is required.
- The licensed engineering contractor shall submit
a list of all subcontractors for approval by the
City of Fort Lauderdale.
- The licensed engineering contractor shall submit
a copy of his/her certificate of liability insurance,
workers compensation and automobile liability insurance
and a copy of his/her qualified contractor license.
Levels of insurance shall be 1 million for general
liabitiy and $500,000 for automobile liability.
In addition to this, the city of ft. lauderdale
shall be named as additional insured as respect
to general liability.
- If re-routing or impacts to traffic in any form
is required during construction, a Temporary Traffic
Modification Application must be submitted. See
Elkin A. Diaz or Tim Welch for application forms.
Note that the maintenance of traffic plan must
be prepared and authorized with signature and date
by a Certified Work Zone Safety Technician, and
the application form must be routed for original
signatures with all revisions authorized by all
parties to the approval.
- Submit a storage and staging plan for approval
by the City of Fort Lauderdale.
- Obtain applicable water meters, domestic, fire
and sewer lateral applications with Elkin Diaz
and return signed agreements/applications with
permit submittal.
- If construction activities require the use of
dewatering, a detailed dewatering plan must be
submitted with the application. The use of well
pointing is preferable. The contractor shall utilize
settling box(es) and perform turbidity tests twice
daily. Disposal of water shall comply with Broward
County DNRP Best Management Procedures with turbidity
less than 2.0 NTU prior to discharge. Under no
circumstance shall water be discharged into the
right-of-way or private property. If no dewatering
will be utilized, the plans must state this.
- Provide a contact list with names, titles, and
phone numbers for office and field construction
representatives.
- A City of Fort Lauderdale engineering inspector
will be assigned to oversee the project. First
contact for field directives shall be through the
assigned inspector, or Elkin A. Diaz, then Tim
Welch, if direction is required.
- The contractor shall contact Public Services
(492-7820/7821), Sunshine, and other applicable
sources for locating all existing facilities in
the right-of-way at a minimum of 48 hours prior
to commencement of construction in addition to
this effort for design purposes. The Engineering
Department will require vacuum locations for all
trenchless construction.
- The City of Fort Lauderdale Engineering Department
must be notified at least 48 hours in advance prior
the commencement of construction in accordance
with item No. 12. A preconstruction meeting is
required for this project, involving city staff,
contractor and engineer of record.
- The Engineering Permit with shop drawings and
any other attachments along with a copy of the
Engineering Contractor license must be on the job
site at all times.
- Any substantial revisions to the approved permit
package must be submitted to and approved by the
City of Fort Lauderdale Engineering Department
prior to construction implementation. Major revisions
require separate engineering permit application
submitted to the front counter and reviewed while
minor revisions are submitted directly to the engineering
plan reviewer. Contact Elkin A. Diaz directly if
there are questions to the magnitude of the revisions.
-
The City of Fort Lauderdale will
provide certification signature for construction
of wastewater facilities, final inspection approval,
or signature prior to issuance of Certificate
of Occupancy after the contractor has submitted
the following:
- Letter of certification for the Engineer
of Record.
- (3) Three sets of as-built drawings signed
and sealed by a Professional Land Surveyor.
The as-built drawings shall be a copy of
the approved plans and shall include the
elevations and locations of all work performed
in the right-of-way.
- A copy of the density report(s) on all
backfill, sub-grade and limerock used in
the right-of-way.
- A letter of acceptance from Broward County
Engineering or FDOT approving the pavement
marking restoration and signage (where
applicable).
-
One density test shall be taken
for each 500 feet of ditch per lift or as directed
by the Engineer. On sanitary sewers and storm
drains, one density test shall be taken between
each manhole run for each lift, or as directed
by the Engineer. Cost of these tests to be paid
for by the City. Any test which fails to meet
specifications will be charged to the contractor,
and additional tests will be taken after the
material has been recompacted.
|
|
|