Post Date:June 20, 2020 10:00 AM

5770 Fort Lauderdale Update Web Graphics_Email Header

UPDATE ON RIO VISTA FORCE MAIN REPLACEMENT PROJECT
July 2020  

Following is an update on operations and activities related to the 48-inch force main replacement project that is currently underway in the Rio Vista neighborhood. 

Construction Activities

-Nearly a mile of new 54-inch force main has been installed, connected, and is currently operational in the Rio Vista neighborhood.

-The new pipe installation included 2,200 linear feet on SE 9 Avenue from SE 12 Street north to SE 8 Street; and 2,500 linear feet along SE 9 Avenue from SE 7 Street north to SE 2 Court in Beverly Heights.

-The new force main has been connected to the existing 54-inch line and is operating properly.  This allowed crews to deactivate and remove the 36-inch above ground bypass line that was previously located along SE 9th Avenue.

-To view video of the pipe installation, visit https://bit.ly/3ekHf5q or visit the City's YouTube channel at https://bit.ly/2YROL17

-Crews are working on the abandonment of the section of the existing 54-inch force main that is no longer in use (see road closure information below). This activity is scheduled to start July 1 and be completed by July 31, 2020.

-Crews will also continue to conduct general restoration work in the construction area.

-Work is underway on installation of the next segment of pipe, which is taking place just south of Rio Vista in the Harbordale neighborhood.

Road Closures for Next Segment of Pipe Installation 

map harbordaleThe City of Fort Lauderdale continues to work with David Mancini & Sons to construct a portion of a new 7.5 mile sewer transmission line to create redundancy, enhance reliability, and improve services for neighbors.

On Wednesday, June 24, the contractor will begin to expand the road closures along SE 10 Avenue, between SE 14 Court and SE 16 Court, to install a new 16-Inch force main. The contractor will do everything possible to complete this segment of work by August 2020, but the schedule may be extended if any unforeseen conditions arise. Work will take place Monday – Friday, from 7 a.m. to 7 p.m., and Saturdays, from 9 a.m. to 5 p.m.

View a flyer with a map of the road closures pdf

The contractor will reach out to homeowners and business owners in the affected area to provide more details.

If you have questions regarding the schedule or access routes, please contact David Mancini, Jr. at 754-264-9594
or dmancinijr@dmsi.co.

Please follow posted signs and drive with caution in the area. We apologize for any inconvenience and thank you for your patience and cooperation as we strive to upgrade our sewer system as quickly as possible.

For more information or questions, contact:
Krishan Kandial, PE., City of Fort Lauderdale 954-828-4019 or kkandial@fortlauderdale.gov

David Mancini Jr., David Mancini & Sons, Inc.
754-264-9594 or dmancinijr@dmsi.co

City of Fort Lauderdale 24-Hour Neighbor Service Center
954-828-8000

Road Closures for Abandonment of 54" Line

54linemap

 

On July 1, 2020, the contractor will start to mobilize equipment needed to permanently abandon the existing 54-inch force main under the Tarpon River.

Starting Monday, July 6, 2020, the contractor may need to close a section of Ponce De Leon Drive at the northeast corner of Hector Park, as well as the intersection of SE 10 Street and South Rio Vista Boulevard on the east side of Virginia Young Park.

View a flyer with a map of the road closures pdf

The contractor will maintain access to properties in the vicinity of the closures.

Construction is scheduled to take place Monday - Friday, from 7 a.m. to 7 p.m., and should last approximately three weeks. The schedule may be extended if any unforeseen conditions arise.

For more information or questions, contact:
David Mancini Jr., David Mancini & Sons, Inc. at 754-264-9594 or dmancinijr@dmsi.co.

 

 

 

  

Environmental Activities and Remediation

-The City of Fort Lauderdale is working with two environmental services companies, E-Sciences and Wood Environmental and Infrastructure Solutions, to remediate areas of George English Lake and the Tarpon River that were impacted by sewer line breaks that took place in late 2019 and early 2020.  

-For the latest updates, please visit www.fortlauderdale.gov/waterwayrestoration.


Learn more about other infrastructure improvement projects underway in Fort Lauderdale.

For More Information

-Neighbors are encouraged to stay up to date by following the City on social media at: 

-Neighbors may also call the City’s 24-hour Neighbor Call Center at 954-828-8000.


Safety Tips:
Flyer pdf

Water Quality Tests:
Water Quality Test Results pdf (as of 01-06-20)

Air Quality Tests:
Test Results and Sampling Locations (12-23-2019 & 12-31-19 through 01-02-20) pdf

Photo Gallery:
http://bit.ly/2RZRaoK 


Sanitary Sewer Overflow (SSO) Reports

Dec. 10, Dec. 20, 2019: Rio Vista/Hector Park (1000 block Ponce De Leon Dr.) and Virginia Young Park (900 block SE 10 St.) pdf

Important Information for Neighbors Affected by Sanitary Sewer Overflows:
Neighbors who live in areas that were affected by the sewer main breaks can click here to get information regarding cleanup efforts and how to file a claim for incurred expenses.pdf