Inflow & Infiltration
What is Inflow & Infiltration?
Inflow and infiltration (I&I) are terms for the ways that stormwater runoff and groundwater (clear water) make their way into sanitary sewer pipes. With inflow, stormwater rapidly flows into sewers via roof drain downspouts, yard drains, storm-sewer cross connections and faulty manhole covers. Inflow is greatest during major storm events and can more than triple wastewater volumes. Infiltration occurs when groundwater water seeps into sanitary sewer pipes through cracks, leaky pipe joints and/or deteriorated manholes.

Why I&I Matters
Excessive I&I in the sewer system creates multiple problems:
- Expensive Treatment: Once stormwater and groundwater mix with wastewater, all the water is treated. This is expensive and impacts the regional system. Reducing excessive I&I in the system saves millions of dollars.
- Reduced System Capacity: Additional water that enters the wastewater system through I&I flows within fixed-capacity sewer pipes. The additional flow consumes capacity that was built to accommodate wastewater flows from existing properties and new developments. During major rain events, the additional flow can exceed the available sewer system capacity, causing overflow issues.
- Water Quality: Exceeding the capacity of the sewer system can result in wastewater overflows and spills into nearby waterways, affecting the water quality.
Reducing Excessive I&I
The City of Fort Lauderdale has prioritized increasing the efficiency and capacity of its sanitary sewer collection system by reducing I&I. The City is implementing a citywide cost-effective I&I reduction program over the next five years to significantly reduce the amount of surface stormwater and subsurface groundwater that enters the City's sanitary sewer system.
Inflow & Infiltration Reduction Program: Sewer System Rehabilitation
The City of Fort Lauderdale is working with LMK Pipe Renewal to make improvements to the City's sewer system in areas where inspections and smoke testing have identified minor defects. The project will start with crews sending cameras into the sewer system to check its condition before and after repairs. They'll also install new access points called cleanouts, replace or fix short sections of sewer pipes that connect properties to the main sewer line and make repairs inside manholes.
Review the following materials to learn more about upcoming sewer system rehabilitation work:
Inflow & Infiltration Reduction Program: Sewer Pipe Video Inspections
The City of Fort Lauderdale is working with Insituform Technologies to inspect sewer mains and laterals throughout the City's sewer system. Crews will access sewer lines through manholes and record videos within the pipes to document their condition. The results of this analysis will be used to plan future sewer system improvement projects. Inspections are expected to be completed in May 2026.
Review the following materials to learn more about upcoming sewer pipe video inspections:
Inflow & Infiltration Reduction Program: Overnight Sewer System Inspections
The City of Fort Lauderdale is working with Ardurra Group Inc. to study the flow of wastewater throughout the City's sewer system over the next three years. This flow analysis is part of the City's ongoing efforts to identify portions of the sewer system where stormwater and groundwater are possibly entering the system, which leads to problems such as increased treatment cost and reduced system capacity. The results of this analysis will be used to plan future sewer system improvement projects.
Review the following materials to learn more about upcoming overnight sewer system inspections:
Archive
- Overnight Wastewater Flow Analysis Schedule Through Tuesday, September 3(PDF, 158KB)
- Map of Overnight Wastewater Flow Analysis Through Tuesday, September 3(PDF, 5MB)
- Overnight Wastewater Flow Analysis Schedule Through Sunday, November 17(PDF, 160KB)
- Map of Overnight Wastewater Flow Analysis Through Sunday, November 17(PDF, 2MB)
- Flyer: Overnight Wastewater Flow Analysis - July 1-3, 2025 (Arterial Roads)(PDF, 125KB)
- Flyer: Overnight Wastewater Flow Analysis - June 29-30, 2025 (Arterial Roads)(PDF, 124KB)
- Schedule / Map: Overnight Wastewater Flow Analysis - June 29-July 3, 2025 (Arterial Roads)(PDF, 2MB)
- Flyer: Overnight Sewer System Inspections - July 6 - August 4, 2025(PDF, 115KB)
- Schedule / Map: Overnight Sewer System Inspections - July 6 - August 4, 2025(PDF, 7MB)
- Flyer: Overnight Sewer System Inspections - August 10 - September 12, 2025(PDF, 115KB)
- Schedule / Map: Overnight Sewer System Inspections - August 10 - September 12, 2025(PDF, 3MB)
- Schedule / Map: Overnight Sewer System Inspections - September 15 - October 15, 2025(PDF, 14MB)
- Flyer: Overnight Sewer System Inspections - September 15 - October 15, 2025(PDF, 117KB)
- Schedule / Map: Overnight Sewer System Inspections - October 15 - November 9, 2025(PDF, 13MB)
- Flyer: Overnight Sewer System Inspections - October 15 - November 9, 2025(PDF, 117KB)
Inflow & Infiltration Reduction Program: Sewer Smoke Testing
The City of Fort Lauderdale is working with Ardurra Group Inc. to conduct smoke testing throughout Fort Lauderdale over the next three years. This common procedure involves blowing smoke through sewer pipes to locate defects that would allow stormwater and groundwater to enter the sewer system. The smoke being used is odorless, non-toxic, non-staining, does not create a fire hazard and will clear within 30 minutes with proper ventilation. Smoke should not enter private properties if they are properly plumbed and vented and if water traps contain water. If smoke enters private property, please ventilate the area, and notify nearby field technicians.
Review the following materials to learn more about upcoming sewer smoke testing:
Archive
- Flyer: Sewer Smoke Testing - Dec 12, 2024 - Jan 24, 2025(PDF, 335KB)
- Flyer: Sewer Smoke Testing - Dec 2024(PDF, 202KB)
- Flyer: Sewer Smoke Testing - May and June 2024(PDF, 205KB)
- Map: Sewer Basin B-6 in Coral Ridge Wed. May 29, 2024 - Mon. June 3, 2024(PDF, 941KB)
- Map: Sewer Basin D-34 in Harbor Beach Tues. June 4, 2024(PDF, 628KB)
- Sewer Smoke Testing - Schedule Through Friday, June 7(PDF, 206KB)
- Map: Sewer Basin A-11 in Downtown Fort Lauderdale & Tarpon River Wed. June 5 - Fri. June 7, 2024(PDF, 2MB)
- Map: Sewer Basin A-99 in Tarpon River Mon., June 10, 2024(PDF, 712KB)
- Map: Sewer Basin A-15 in Rio Vista: Tues., June 11 - Wed., June 12, 2024(PDF, 656KB)
- Map: Sewer Basin A-27 in Middle River Terrace: Thurs./Fri., June 13-14 & Mon./Tues., June 17-18, 2024(PDF, 784KB)
- Sewer Smoke Testing - Schedule Through Tuesday, June 18(PDF, 205KB)
- Sewer Smoke Testing - Schedule Through Tuesday, June 25(PDF, 205KB)
- Map: Sewer Basin A-15 in Rio Vista: Tues./Weds., June 18-19, 2024(PDF, 6MB)
- Map - Sewer Basin A-27 in Middle River Terrace: Thurs./Fri., June 20-21 & Mon./Tues., June 24-25, 2024(PDF, 6MB)
- Sewer Smoke Testing - Schedule Through Monday, July 8(PDF, 205KB)
- Map - Sewer Basin A-29 in South Middle River & Middle River Terrace: Tuesday, June 25 - Tuesday, July 2, 2024(PDF, 24MB)
- Map - Sewer Basin A-14 in Lake Ridge, Poinsettia Heights, Laudergate Isles & Bal Harbour: Tuesday, July 2 - Monday, July 8, 2024(PDF, 24MB)
- Sewer Smoke Testing Schedule Through Friday, July 12, 2024(PDF, 206KB)
- Map - Sewer Basin A-14 in Lake Ridge, Poinsettia Heights, Laudergate Isles & Bal Harbour: Monday, July 8 - Thursday, July 11(PDF, 3MB)
- Map - Sewer Basin D-20 in Las Olas Isles (Isle of Palm Drive) and Sewer Basin D-21 in Riviera Isles (Flamingo Drive): Friday, July 12(PDF, 3MB)
- Map - Sewer Basin D-7, D-8 and D-9 in Nurmi Isles: Friday, July 12(PDF, 3MB)
- Sewer Smoke Testing Schedule Through Friday, July 19(PDF, 209KB)
- Map - Sewer Basin B-12 Lake Estates, Bay Colony and Landings: Wednesday, July 17 - Friday, July 19(PDF, 4MB)
- Map - Sewer Basin D-11 Hendricks and Venice Isles (Hendricks Isle): Tuesday, July 16(PDF, 4MB)
- Map - Sewer Basin D-19 Las Olas Isles (Royal Plaza Drive): Tuesday, July 16(PDF, 3MB)
- Map - Sewer Basin D-2 Seven Isles (Seven Isles Drive, De Soto Drive and Barcelona Drive): Tuesday, July 16(PDF, 4MB)
- Map - Sewer Basin D-20 in Las Olas Isles (Isle of Palm Drive) and Sewer Basin D-21 in Riviera Isles (Flamingo Drive): Monday, July 15(PDF, 3MB)
- Map - Sewer Basin D-24 Sunrise Key: Tuesday, July 16(PDF, 3MB)
- Map - Sewer Basin D-37 Las Olas Isles (Lido Drive): Tuesday, July 16(PDF, 4MB)
- Map - Sewer Basin D-7, D-8 and D-9 in Nurmi Isles: Monday, July 15(PDF, 3MB)
- Smoke Test Schedule on Arterial Roads - January 6-10, 2025(PDF, 2MB)
- Map of Smoke Testing Jan. 20-30: Sewer Basin B1 in Coral Ridge Country Club Estates & Coral Ridge(PDF, 3MB)
- Map of Smoke Testing Jan. 31 - Feb. 17: Sewer Basin B10 in Boulevard Park Isles, Imperial Point and Knoll Ridge (February 10-11)(PDF, 3MB)
- Map of Smoke Testing Jan. 13-17: Sewer Basin B11 in Knoll Ridge(PDF, 3MB)
- Smoke Test Schedule Through February 17, 2025(PDF, 2MB)
- Map of Smoke Testing Feb. 24 - Mar. 3: Sewer Basin A-12 in Tarpon River, River Oaks, and Croissant Park(PDF, 3MB)
- Map of Smoke Testing Feb. 20-21: Sewer Basin D-29 in Harbor Beach(PDF, 1MB)
- Map of Smoke Testing Feb. 20-21: Sewer Basin D-41 in Central Beach Alliance(PDF, 2MB)
- Smoke Testing Schedule February 11 through March 10(PDF, 2MB)
- Map of Smoke Testing Mar. 4-7: Sewer Basin A-22 in Poinsettia Heights(PDF, 2MB)
- Map of Smoke Testing Mar. 10: Sewer Basin D-38 in Riviera Isles(PDF, 1MB)
- Flyer - Sewer Smoke Testing - February 20 - March 10, 2025(PDF, 177KB)
- Flyer: Sewer Smoke Testing - March 11-17, 2025(PDF, 175KB)
- Flyer: Sewer Smoke Testing - March 18 - April 11, 2025(PDF, 178KB)
- Schedule: Sewer Smoke Testing March 11 - April 11, 2025(PDF, 2MB)
- Maps: Sewer Smoke Testing March 11 - April 11, 2025(PDF, 18MB)
- Flyer: Sewer Smoke Testing - April 14-24, 2025(PDF, 173KB)
- Flyer: Sewer Smoke Testing - April 26, 2025 to May 6, 2025(PDF, 173KB)
- Flyer: Sewer Smoke Testing - May 7-23, 2025(PDF, 171KB)
- Schedule: Sewer Smoke Testing April 14 - May 23, 2025(PDF, 3MB)
- Maps: Sewer Smoke Testing April 14 - May 23, 2025(PDF, 108MB)
- Flyer: Sewer Smoke Testing - May 8-19, 2025(PDF, 166KB)
- Schedule: Sewer Smoke Testing May 8-19, 2025(PDF, 2MB)
- Maps: Sewer Smoke Testing May 8-19, 2025(PDF, 5MB)
- Flyer: Sewer Smoke Testing - May 23, 2025, to June 6, 2025(PDF, 172KB)
- Schedule: Sewer Smoke Testing - May 23, 2025, to June 6, 2025(PDF, 2MB)
- Maps: Sewer Smoke Testing May 23, 2025, to June 6, 2025(PDF, 6MB)
- Flyer: Sewer Smoke Testing in Sunset - June 17-20, 2025(PDF, 207KB)
- Private Property Access Consent Form(PDF, 167KB)
- Maps: Sewer Smoke Testing in Sunset - June 17-20, 2025(PDF, 2MB)
- Schedule: Sewer Smoke Testing - June 23-27, 2025(PDF, 2MB)
- Sewer Smoke Testing - June 23-24, 2025 (Arterial Roads)(PDF, 189KB)
- Sewer Smoke Testing - June 25-27, 2025 (Arterial Roads)(PDF, 189KB)
How can the community help with I&I reduction efforts?
A significant level of I&I occurs on private property. The City will be engaging in efforts to involve and educate neighbors on how they can help reduce I&I within the sanitary sewer system.
- Avoid planting trees and shrubs over sewer lines on private property (known as sewer laterals). The roots can damage the structure of the sewer pipes and cause leaks.
- Make sure that sewer cleanouts are properly capped. The plastic caps tend to be broken by lawn mowers. Replacement lids are available at local hardware stores.
- Proactively replace any known broken, leaky or problem sections of sewer pipe that are located on your property.
Contact Us
For more information or questions, contact: